DFW related construction projects

DFW Construction News

Public construction and infrastructure notes gathered from official source data. These are regional DFW news briefs, not White Stone project announcements.

This page tracks publicly listed Dallas-Fort Worth infrastructure activity that may matter to owners, developers, survey teams, design teams, and contractors. A project appearing here does not mean White Stone is connected to, contracted for, or endorsing the project.

Updated weekly

Source-linked DFW construction project notes

Johnson CountyDFW Construction

Johnson FM 157 project highlights construct new road

Fort Worth District project data shows construct new road on FM 157 in Johnson County.

TxDOT Project Tracker data shows construct new road tied to FM 157 in Johnson County. The listed limits run from BU 287P to US 67. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $154.5M.

  • Limits: BU 287P to US 67.
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $154.5M.
  • Official project reference: A00033759.
Source: TxDOT Project Tracker
Wise CountyDFW Construction

Wise US 81 project highlights widen road - add lanes

Fort Worth District project data shows widen road - add lanes on US 81 in Wise County.

TxDOT Project Tracker data shows widen road - add lanes tied to US 81 in Wise County. The listed limits run from NORTH OF PIONEER RD. to TARRANT/WISE COUNTY LINE. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $338.3M.

  • Limits: NORTH OF PIONEER RD. to TARRANT/WISE COUNTY LINE.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $338.3M.
  • Official project reference: A00007731.
Source: TxDOT Project Tracker
Johnson CountyDFW Construction

Johnson US 67 project highlights widen road - add lanes

Fort Worth District project data shows widen road - add lanes on US 67 in Johnson County.

TxDOT Project Tracker data shows widen road - add lanes tied to US 67 in Johnson County. The listed limits run from SOMERVELL COUNTY LINE to FM 1434. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $239.8M.

  • Limits: SOMERVELL COUNTY LINE to FM 1434.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $239.8M.
  • Official project reference: A00063324.
Source: TxDOT Project Tracker
Tarrant CountyDFW Construction

Tarrant IH 820 project highlights widen road - add lanes

Fort Worth District project data shows widen road - add lanes on IH 820 in Tarrant County.

TxDOT Project Tracker data shows widen road - add lanes tied to IH 820 in Tarrant County. The listed limits run from Navajo Trail/Cahoba Drive to Marine Creek Parkway. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $888.3M.

  • Limits: Navajo Trail/Cahoba Drive to Marine Creek Parkway.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $888.3M.
  • Official project reference: A00130087.
Source: TxDOT Project Tracker
Parker CountyDFW Construction

Parker SH 171 project highlights widen road - add lanes

Fort Worth District project data shows widen road - add lanes on SH 171 in Parker County.

TxDOT Project Tracker data shows widen road - add lanes tied to SH 171 in Parker County. The listed limits run from Johnson County Line to BB Fielder Rd. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $566.2M.

  • Limits: Johnson County Line to BB Fielder Rd.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $566.2M.
  • Official project reference: A00224053.
Source: TxDOT Project Tracker
Johnson CountyDFW Construction

Johnson SH 171 project highlights widen road - add lanes

Fort Worth District project data shows widen road - add lanes on SH 171 in Johnson County.

TxDOT Project Tracker data shows widen road - add lanes tied to SH 171 in Johnson County. The listed limits run from SH 174 to US 377. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $739.8M.

  • Limits: SH 174 to US 377.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $739.8M.
  • Official project reference: A00224056.
Source: TxDOT Project Tracker
Tarrant CountyDFW Construction

Tarrant BU 287P project highlights widen road - add lanes

Fort Worth District project data shows widen road - add lanes on BU 287P in Tarrant County.

TxDOT Project Tracker data shows widen road - add lanes tied to BU 287P in Tarrant County. The listed limits run from Bonds Ranch Road to US 81/287. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $203.2M.

  • Limits: Bonds Ranch Road to US 81/287.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $203.2M.
  • Official project reference: A00224052.
Source: TxDOT Project Tracker
Tarrant CountyDFW Construction

Tarrant FM 1187 project highlights widen road - add lanes

Fort Worth District project data shows widen road - add lanes on FM 1187 in Tarrant County.

TxDOT Project Tracker data shows widen road - add lanes tied to FM 1187 in Tarrant County. The listed limits run from US 377 to CHISHOLM TRAIL PARKWAY. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $273.7M.

  • Limits: US 377 to CHISHOLM TRAIL PARKWAY.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $273.7M.
  • Official project reference: A00061857.
Source: TxDOT Project Tracker
Parker CountyDFW Construction

Parker FM 3325 project highlights widen road - add lanes

Fort Worth District project data shows widen road - add lanes on FM 3325 in Parker County.

TxDOT Project Tracker data shows widen road - add lanes tied to FM 3325 in Parker County. The listed limits run from FM 1886 to IH 20. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $275.1M.

  • Limits: FM 1886 to IH 20.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $275.1M.
  • Official project reference: A00061779.
Source: TxDOT Project Tracker
Hood CountyDFW Construction

Hood SH 171 project highlights widen road - add lanes

Fort Worth District project data shows widen road - add lanes on SH 171 in Hood County.

TxDOT Project Tracker data shows widen road - add lanes tied to SH 171 in Hood County. The listed limits run from US 377 to Parker County Line. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $173.8M.

  • Limits: US 377 to Parker County Line.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $173.8M.
  • Official project reference: A00224055.
Source: TxDOT Project Tracker
Tarrant CountyDFW Construction

Tarrant SS 170 project highlights construct new road

Fort Worth District project data shows construct new road on SS 170 in Tarrant County.

TxDOT Project Tracker data shows construct new road tied to SS 170 in Tarrant County. The listed limits run from E of IH 35 to Intermodal Parkway. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $95.4M.

  • Limits: E of IH 35 to Intermodal Parkway.
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $95.4M.
  • Official project reference: A00224098.
Source: TxDOT Project Tracker
Johnson CountyDFW Construction

Johnson FM 157 project highlights widen road - add lanes

Fort Worth District project data shows widen road - add lanes on FM 157 in Johnson County.

TxDOT Project Tracker data shows widen road - add lanes tied to FM 157 in Johnson County. The listed limits run from County Road 510 to US 67. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $108.7M.

  • Limits: County Road 510 to US 67.
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $108.7M.
  • Official project reference: A00221425.
Source: TxDOT Project Tracker

White Stone services

Need survey, engineering, mapping, or environmental support?

Use the White Stone service pages for company work. Use this page only as a public news reference.